Modular containers on Mount Snowdon
Reparations to Mount Snowdon pipeline works supported by temporary units provided by Algeco.
Contents |
[edit] Brief
Snowdon or Yr Wyddfa, is the highest mountain in Wales, at an elevation of 1,085 metres above sea level, and the highest point in the British Isles outside the Scottish Highlands. Located in Snowdonia National Park in Gwynedd, the mountain is also home to the Cwm Dyli hydro-electric power station, owned by RWE Renewables.
The concrete structures supporting the pipeline that runs down the side of Mount Snowdon feeding the power station are relatively old, and so needed to be replaced. Jennings Building & Civil Engineering Ltd were appointed by RWE to carry out the maintenance.
[edit] Solution
Due to the particularly dangerous location of the project, Jennings needed to ensure that their employees’ safety and welfare was of top priority. They selected Algeco to provide modular accommodation to the site, due to our reputation for health and safety, reliability and high quality products.
The mountainous location of the site meant that any accommodation would need to be transported by helicopter, so Algeco needed to select a lightweight solution that met the weight restrictions (1200kg).
Algeco’s storage containers were under this weight, and the company’s Deeside depot changed them all into small canteens (added a sink, worktop, electrics and lighting). However, due to the weight restrictions, the sink and worktops couldn’t be fitted until the storage containers were on the mountain as the furniture would have made the containers too heavy.
[edit] Results
Algeco provided Jennings Building & Civil Works with 7 storage containers, on hire for 50 weeks, which were dotted up and down Mount Snowdon to provide the workers with relief from the cold, and a space to recharge and take a break.
The replacement of the pipe support structures will limit the amount of unplanned maintenance and disruptions for the Cwm Dyli hydro-electric power station.
[edit] Comment
Phil Boyes, Agent for Jennings Building & Civil Works, said: “We are really impressed that Algeco managed to find a solution lightweight enough to be transported by helicopter, but also meet our high expectations for health and safety on such an unpredictable site”.
“The site accommodation that Algeco has provided will ensure our employees have a safe place to recoup during their working day.”
Mark Fyfe, Infrastructure Business Development Manager at Algeco, said: “This was a first for Algeco. Having our units flown in by helicopter to a mountainous area is not something that we have done before, but when our customers come to us with a bespoke project, we will always do our very best to find a solution to fit their needs.
“We are pleased that Jennings Building & Civil Engineering are satisfied with our solution and we look forward to working with them again in the future.”
This article was supplied via Press Release as "Algeco supports reparations to Mount Snowdon pipeline works" along with images dated February 16, 2023.
[edit] Related articles on Designing Buildings
- Construction problems avoided by using a modular approach.
- Design for deconstruction.
- Factory-made housing.
- Flat pack.
- Modular buildings in the educational sector.
- Modular classrooms: The Friars Primary School extension.
- Off-site construction.
- Plug and play skyscrapers.
- Pod.
- Temporary and interim buildings.
- Temporary demountable structures.
- Temporary flood defences.
- Temporary services on construction sites.
- Temporary structures.
- Temporary use.
- Temporary works.
- Volumetric modular construction.
- Volumetric unit.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.